Finding better ways to provide the materials the world needs
Our business
We operate in 35 countries where our 60,000 employees are working to find better ways to provide the materials the world needs
Our purpose in action
Continuous improvement and innovation are part of our DNA
Innovation
The need for innovation is greater than ever
We supply the metals and minerals used to help the world grow and decarbonise
Iron Ore
The primary raw material used to make steel, which is strong, long-lasting and cost-efficient
Lithium
The lightest of all metals, it is a key element needed for low-carbon technologies
Copper
Tough but malleable, corrosion-resistant and recyclable, and an excellent conductor of heat and transmitter of electricity
Bringing to market materials critical to urbanisation and the transition to a low-carbon economy
Oyu Tolgoi
One of the most modern, safe and sustainable operations in the world
Rincon Project
A long-life, low-cost and low-carbon lithium source
Simandou Project
The world’s largest untapped high-grade iron ore deposit
Providing materials the world needs in a responsible way
Climate Change
We’re targeting net zero emissions by 2050
Nature solutions
Our nature-based solutions projects complement the work we're doing to reduce our Scope 1 and 2 emissions
Enabling ESG transparency
Our START™ initiative tracks traceability and responsible production of Rio Tinto materials.
We aim to deliver superior returns to our shareholders while safeguarding the environment and meeting our obligations to wider society
Reports 2024
Download our 2024 suite of reports, including our 2024 Taxes and Royalties Paid Report, detailing $8.4 billion of taxes and royalties paid globally during the year
Get the latest news, stories and updates
Things You Can't Live Without
Our podcast discussing what needs to happen to create a sustainable future for the everyday items we have come to rely on
Refuelling the mining industry
How can we power the world’s biggest machines with new fuel solutions?
Forging a low-carbon future
How we're working to decarbonise iron ore and steel
Discover more about life at Rio Tinto
Graduates and students
If you want to drive real change, we have just the place to do it
Empowering families with flexibility
Supporting new parents of any gender with equal access to parental leave
Available jobs
Join our team
PERTH, Australia--(BUSINESS WIRE)-- Rio Tinto and Hancock Prospecting will invest $1.61 billion (Rio Tinto share $0.8 billion) to develop the Hope Downs 2 iron ore project in Western Australia’s Pilbara region.
The Hope Downs 2 project, to mine Rio Tinto and Hancock Prospecting’s Hope Downs 2 and Bedded Hilltop deposits, has now received all necessary State and Federal Government approvals.
The two new above-water-table iron ore pits will have a combined total annual production capacity of 31 million tonnes and will sustain production from the Hope Downs Joint Venture into the future.
Rio Tinto Iron Ore Chief Executive Simon Trott said: “Approval of Hope Downs 2 is a key milestone for Rio Tinto, as we invest in the next generation of iron ore mines in the Pilbara.
“These projects are part of our strategy to continue investing in Australian iron ore and to sustain Pilbara production for decades to come, supporting jobs, local businesses and the state and national economies.
“The Pilbara has been critical to global steel supply for more than 60 years, and we are committed to ensuring it remains so well into the future.”
Rio Tinto has engaged with the Nyiyaparli, Banjima and the Ngarlawangga Peoples, along with relevant government stakeholders, to ensure the responsible management of heritage and the environment in development of the project.
The project includes new non-process infrastructure precincts, railway crossings and haul roads, as well as realigning a 6-kilometre section of the Great Northern Highway.
Ore mined at the two sites will be transported to Hope Downs 1 for processing, with first ore from the deposits and associated infrastructure scheduled for 2027.
More than 950 jobs will be created during construction and, once operational, the Hope Downs 2 project will help sustain a workforce of about 1000 full time equivalent roles at Greater Hope Downs.
Hope Downs 2 is part of Rio Tinto’s tranche of replacement projects that underpin the company’s ongoing commitment to the Pilbara, and which will have combined total capacity of about 130Mtpa2.
During the next three years (2025-2027), Rio Tinto expects to invest more than $13 billion on new mines, plant and equipment.
The company has a clear pathway to achieve and sustain mid-term system capacity of 345 to 360Mtpa from its Pilbara iron ore business, with a pre-feasibility study also underway on the Rhodes Ridge project, the Pilbara’s best undeveloped iron ore deposit.
Additional information
Rio Tinto and Hancock Prospecting are equal partners in the Hope Downs Joint Venture.
The Joint Venture was originally established in 2006, with Rio Tinto and Hancock Prospecting's shared history extending back to the early 1960's.
Hope Downs 1 started production in 2007, followed by Hope Downs 4, with first ore in 2013.
Footnotes
1 All currency figures are in US dollars and on a 100 per cent basis, unless otherwise specified. The capital for the project is already included in the Group’s replacement capital guidance.
2 Subject to timing of full capacity. The replacement projects include Western Range which, as previously announced, was opened on 6 June 2025, Brockman Syncline 1, as announced on 6 March 2025, Hope Downs 2, West Angelas and Greater Nammuldi.
View source version on businesswire.com: https://www.businesswire.com/news/home/20250623938934/en/
Please direct all enquiries to media.enquiries@riotinto.com
Media Relations, United Kingdom Matthew Klar M +44 7796 630 637 David Outhwaite M +44 7787 597 493
Media Relations, Australia Matt Chambers M +61 433 525 739 Michelle Lee M +61 458 609 322 Rachel Pupazzoni M +61 438 875 469
Media Relations, Canada Simon Letendre M +1 514 796 4973 Malika Cherry M +1 418 592 7293 Vanessa Damha M +1 514 715 2152
Media Relations, US Jesse Riseborough M +1 202 394 9480
Investor Relations, United Kingdom Rachel Arellano M: +44 7584 609 644 David Ovington M +44 7920 010 978 Laura Brooks M +44 7826 942 797 Weiwei Hu M +44 7825 907 230
Investor Relations, Australia Tom Gallop M +61 439 353 948 Phoebe Lee M +61 413 557 780
Rio Tinto plc 6 St James’s Square London SW1Y 4AD United Kingdom T +44 20 7781 2000 Registered in England No. 719885
Rio Tinto Limited Level 43, 120 Collins Street Melbourne 3000 Australia T +61 3 9283 3333 Registered in Australia ABN 96 004 458 404
This announcement is authorised for release to the market by Andy Hodges, Rio Tinto’s Group Company Secretary.
riotinto.com
Category: Pilbara
Source: Rio Tinto