Finding better ways to provide the materials the world needs
Our business
We operate in 35 countries where our 57,000 employees are working to find better ways to provide the materials the world needs
Our purpose in action
Continuous improvement and innovation are part of our DNA
Innovation
The need for innovation is greater than ever
We supply the metals and minerals used to help the world grow and decarbonise
Iron Ore
The primary raw material used to make steel, which is strong, long-lasting and cost-efficient
Lithium
The lightest of all metals, it is a key element needed for low-carbon technologies
Copper
Tough but malleable, corrosion-resistant and recyclable, and an excellent conductor of heat and transmitter of electricity
Bringing to market materials critical to urbanisation and the transition to a low-carbon economy
Oyu Tolgoi
One of the most modern, safe and sustainable operations in the world
Rincon Project
A long-life, low-cost and low-carbon lithium source
Simandou Project
The world’s largest untapped high-grade iron ore deposit
Providing materials the world needs in a responsible way
Climate Change
We’re targeting net zero emissions by 2050
Nature solutions
Our nature-based solutions projects complement the work we're doing to reduce our Scope 1 and 2 emissions
Decarbonisation progress update
We have a clear plan on decarbonisation - find out more about our progress in 2024
We aim to deliver superior returns to our shareholders while safeguarding the environment and meeting our obligations to wider society
Investor seminars
Our Investor seminar will be held in London on 4 December, and our Decarbonisation update on 5 December
Get the latest news, stories and updates
Things you can't live without
Our podcast discussing what needs to happen to create a sustainable future for the everyday items we have come to rely on
The 'f' word of innovation
How unlocking innovation requires a change of mindset
Reducing titanium oxide's carbon footprint
Our BlueSmelting technology could drastically reduce carbon emissions during ore processing
Discover more about life at Rio Tinto
Graduates and students
If you want to drive real change, we have just the place to do it
Empowering families with flexibility
Supporting new parents of any gender with equal access to parental leave
Available jobs
Join our team
LONDON--(BUSINESS WIRE)-- All conditions have now been satisfied for Rio Tinto’s investment to develop the Simandou high-grade iron ore deposit in Guinea, including the completion of necessary Guinean and Chinese regulatory approvals. The transaction is expected to complete during the week of 15 July 2024.
Along with the recent approval by the Board of Simfer1, this allows Simfer to invest in and fund its share of co-developed rail and port infrastructure being progressed in partnership with Winning Consortium Simandou2 (WCS), Baowu and the Republic of Guinea.
More than 600 kilometres of new multi-use trans-Guinean railway together with port facilities will allow the export of up to 120 million tonnes per year of mined iron ore by Simfer and WCS from their respective Simandou mining concessions in the southeast of the country3. Together, this will be the largest greenfield integrated mine and infrastructure investment in Africa.
Rio Tinto Executive Committee lead for Guinea and Copper Chief Executive Bold Baatar said: “We thank the Government of Guinea, Chinalco, Baowu and WCS for their partnership in reaching this milestone towards developing the world class Simandou project.
“Simandou will deliver a significant new source of high-grade iron ore that will strengthen Rio Tinto’s portfolio for the decarbonisation of the steel industry, along with trans-Guinean rail and port infrastructure that can make a significant contribution to the country’s economic development.”
Under the terms of the transaction, Simfer will acquire a participation in the WCS project companies constructing rail and port infrastructure, commit to perform a portion of the construction works itself and commit to funding its share of the overall co-developed infrastructure cost, in an aggregate amount of approximately $6.5 billion (Rio Tinto share approximately $3.5 billion)4.
Chalco Iron Ore Holdings Ltd (CIOH) has now paid its share of capital expenditures incurred or required by Simfer to progress critical works up to completion. A first payment of approximately $410 million, for expenditures until the end of 2023, was made on 28 June 2024, and a second payment of approximately $575 million, for 2024 expenditures, was made on 11 July 2024. These amounts settle all expenditures incurred up to date.
The co-developed infrastructure capacity and associated cost will be shared equally between Simfer, which will develop, own and operate a 60 million tonne per year5 mine in blocks 3 and 4 of the Simandou Project, and WCS, which is developing blocks 1 and 2.
Under the co-development arrangement, Simfer and WCS will deliver separate infrastructure scopes to leverage expertise. Simfer will construct the approximately 70 kilometre Simfer spur rail line and a 60 million tonne per year transhipment vessel (TSV) port, while WCS will construct the dual track approximately 536 kilometre main rail line, the approximately 16 kilometre WCS spur rail line and a 60 million tonne per year barge port.
Once complete, all co-developed infrastructure and rolling stock will be transferred to and operated by the Compagnie du Transguinéen (CTG) joint venture, in which Simfer and WCS each hold a 42.5% equity stake and the Guinean State a 15% equity stake6.
First production from the Simfer mine is expected in 2025, ramping up over 30 months to an annualised capacity of 60 million tonnes per year5 (27 million tonnes Rio Tinto share). The mine will initially deliver a single fines product before transitioning to a dual fines product of blast furnace and direct reduction ready ore.
Simfer's capital funding requirement for the Simandou project as a whole is estimated to be approximately $11.6 billion, of which Rio Tinto's share is approximately $6.2 billion, broken down as follows.
US dollars in billions (nominal terms)
Simfer
capex
Rio Tinto share
Mine and TSVs, owned and operated by Simfer
Development of an initial 60Mt/a mine at Simandou South (blocks 3 & 4), to be constructed by Simfer
$5.1
$2.7
Co-developed infrastructure, owned and operated by CTG once complete
Simfer scope (funded 100% by Simfer during construction)
Rail: a 70 km rail-spur from Simfer mine to the mainline, including rolling stock Port: construction of a 60Mt/a TSV port
$3.5
$1.9
WCS scope (funded 34% by Simfer during construction)
Port and rail infrastructure including an approximately 552 km trans-Guinean heavy haul rail system, comprised of a 536 km mainline and a 16 km WCS rail spur
$3.0
$1.6
Total capital expenditure (nominal terms)
$11.6
$6.27
Rio Tinto's share of expected capital investment remaining to be spent from 1 January 2024 is to be $5.7 billion. Rio Tinto's expected funding requirements for 2024 and 2025 are included in its share of capital investment guidance for this period, with project funding expected to extend beyond this timeframe.
Further details on the Simandou project can be found in the 2023 Investor Seminar presentation at https://www.riotinto.com/en/invest/investor-seminars.
As Chinalco, Baowu, China Rail Construction Corporation and China Harbour Engineering Company are Chinese state-owned entities, and given Chinalco indirectly holds 11.2% of shares in the Rio Tinto Group, they, and WCS, may be considered to be associates of a related party of Rio Tinto for the purpose of the UK Listing Rules. Rio Tinto’s funding commitment pursuant to the infrastructure co-development arrangement (Rio Tinto share $3.5bn) is a smaller related party transaction for the purposes of Listing Rule 11.1.10R and this announcement is, therefore, made in accordance with Listing Rule 11.1.10R(2)(c).
___________________________
1 Approval has been granted by the Board of Simfer Jersey Limited, a joint venture between the Rio Tinto Group (53%) and Chalco Iron Ore Holdings Ltd (CIOH) (47%), a Chinalco-led joint venture of leading Chinese SOEs (Chinalco (75%), Baowu (20%), China Rail Construction Corporation (2.5%) and China Harbour Engineering Company (2.5%)). Simfer Infraco Guinée S.A.U. will deliver Simfer Jersey’s scope of the co-developed rail and port infrastructure, and is, on the date of this notice, a wholly-owned indirect subsidiary of Simfer Jersey Limited, but will be co-owned by the Guinean State (15%) after closing of the co-development arrangements. Simfer S.A. is the holder of the mining concession covering Simandou Blocks 3 & 4, and is owned by the Guinean State (15%) and Simfer Jersey Limited (85%).
2 WCS is the holder of Simandou North Blocks 1 & 2 (with the Government of Guinea holding a 15% interest in the mining vehicle and WCS holding 85%) and associated infrastructure. WCS was originally held by WCS Holdings, a consortium of Singaporean company, Winning International Group (50%) and Weiqiao Aluminium (part of the China Hongqiao Group) (50%). On 19 June 2024, Baowu Resources completed the acquisition of a 49% share of WCS mine and infrastructure projects with WCS Holdings holding the remaining 51%. In the case of the mine, Baowu also has an option to increase to 51% during operations. After Closing, Simfer will hold 34% of the shares in the WCS infrastructure entities during construction with WCS holding the remaining 66%.
3 WCS holds the mining concession for Blocks 1 and 2, while Simfer S.A. holds the mining concession for blocks 3 and 4. Simfer and WCS will independently develop their mines.
4 A true-up mechanism will apply between Simfer and WCS to equalise most of their costs of constructing the co-developed rail and port infrastructure. The figures shown here are pre-equalisation.
5 The estimated annualised capacity of approximately 60 million dry tonnes per annum iron ore for the Simandou life of mine schedule was previously reported in a release to the Australian Securities Exchange dated 6 December 2023 titled “Simandou iron ore project update”. Rio Tinto confirms that all material assumptions underpinning that production target continue to apply and have not materially changed.
6 Ownership of the rail and port infrastructure will transfer from CTG to the Guinean State after a 35 year Operations Period, with Simfer retaining access rights on a non-discriminatory basis and at least equivalent to all Third Party Users.
7 By the end of 2023, Rio Tinto spent $0.5 billion (Rio Tinto share) to progress critical path works. Rio Tinto’s share of expected capital investment remaining to be spent from 1 January 2024 was $5.7 billion.
This announcement is authorised for release to the market by Andy Hodges, Rio Tinto’s Group Company Secretary.
View source version on businesswire.com: https://www.businesswire.com/news/home/20240621382292/en/
Please direct all enquiries to media.enquiries@riotinto.com
Media Relations, United Kingdom Matthew Klar M +44 7796 630 637 David Outhwaite M +44 7787 597 493
Media Relations, Australia Matt Chambers M +61 433 525 739 Jesse Riseborough M +61 436 653 412 Alyesha Anderson M +61 434 868 118 Michelle Lee M +61 458 609 322
Media Relations, Americas Simon Letendre M +1 514 796 4973 Malika Cherry M +1 418 592 7293 Vanessa Damha M +1 514 715 2152
Investor Relations, United Kingdom David Ovington M +44 7920 010 978 Laura Brooks M +44 7826 942 797
Investor Relations, Australia Tom Gallop M +61 439 353 948 Amar Jambaa M +61 472 865 948
Rio Tinto plc 6 St James’s Square London SW1Y 4AD United Kingdom T +44 20 7781 2000 Registered in England No. 719885
Rio Tinto Limited Level 43, 120 Collins Street Melbourne 3000 Australia T +61 3 9283 3333 Registered in Australia ABN 96 004 458 404
riotinto.com
Category: Simandou
Source: Rio Tinto
How we process personal data provided or obtained through this website.
With the exception of the use of cookies, Rio Tinto generally does not seek to collect personal data through this website. However if you choose to provide personal data to Rio Tinto through this website (for example, by sending us an email), we will process that personal data to answer your query and if relevant, to manage our business relationship with you or your company. We won't process that personal data for other purposes except where required to meet our legal obligations or otherwise as authorised by law and notified to you.
If you choose to subscribe to our media releases or other communications, you can unsubscribe at any time (by following the instructions in the email or by contacting us).
With your consent, our website uses cookies to distinguish you from other users of our website. This helps us to provide you with a good experience when you browse our website and also allows us to improve our site. A cookie is a small file of letters and numbers that we store on your browser or the hard drive of your computer if you agree. Cookies contain information that is transferred to your computer's hard drive.
As some data privacy laws regulate IP addresses and other information collected through the use of cookies as personal data, Rio Tinto’s processing of such personal data needs to comply with its Data Privacy Standard (see Part 1 of our Privacy Policy), and also applicable data privacy laws.
With the exception of the use of cookies (explained below), Rio Tinto generally does not seek to collect personal data through this website. However if you choose to provide personal data to Rio Tinto through this website (for example, by sending us an email), we will process that personal data to answer your query and if relevant, to manage our business relationship with you or your company. We won't process that personal data for other purposes except where required to meet our legal obligations or otherwise as authorised by law and notified to you.
Part 1 of this Privacy Policy contains the Rio Tinto Data Privacy Standard, which provides an overview of Rio Tinto’s approach to personal data processing. There is additional information in the appendices to the Data Privacy Standard, including information about disclosures, trans-border data transfers, the exercise of data subject rights and how to make complaints or obtain further information relating to Rio Tinto’s processing of your personal data.
If you choose to subscribe to our media releases or other communications, you can unsubscribe at any time (by following the instructions in the email or by contacting us at digital.comms@riotinto.com).
With your consent, our website uses cookies to distinguish you from other users of our website. This helps us to provide you with a good experience when you browse our website and also allows us to improve our site.
A cookie is a small file of letters and numbers that we store on your browser or the hard drive of your computer if you agree. Cookies contain information that is transferred to your computer's hard drive.
As some data privacy laws regulate IP addresses and other information collected through the use of cookies as personal data, Rio Tinto’s processing of such personal data needs to comply with its Data Privacy Standard (see Part 1 of this Privacy Policy), and also applicable data privacy laws.
These Cookies are used to provide a better user experience on the site, such as by measuring interactions with particular content or remembering your settings such as language or video playback preferences.
These Cookies allow us to analyse site usage in order to evaluate and improve its performance. They help us know how often you come to our site and when, how long you stay and any performance issues you experience whilst you are on our site.
These Cookies are used by advertising companies to inform and serve personalised ads to your devices based on your interests. These Cookies also facilitate sharing information with social networks or recording your interactions with particular ads.