Operations & financial report
Hamersley Iron
(Rio Tinto: 100 per cent)
Hamersley Iron operates nine mines in Western Australia, including three mines in joint ventures, about 700 kilometres of dedicated railway, and port and infrastructure facilities located at Dampier. These assets are run as a single operation managed and maintained by Pilbara Iron.
The final phase in ramping up Pilbara infrastructure to 220 million tonnes of annual capacity is well under way. Dampier port’s two terminals now account for a combined capacity of 140 Mt/a. With the completion of Junction South East, Yandicoogina mine capacity has been expanded to 52 Mt/a, and brownfield mine expansions at Marandoo, Nammuldi and Mount Tom Price have been completed.
The new Hope Downs mine, owned in 50:50 joint venture with Hope Downs Iron Ore Pty Ltd (owned by Hancock Prospecting Pty Ltd), but managed by RTIO, began production in November, a full quarter ahead of schedule, and the first train was loaded in mid December.
Approval was granted for the US$1.52 billion Brockman 4 mine, 60 kilometres north west of Tom Price, which will begin ramp up in 2010 to 22 Mt/a. The mine will be connected to the main network via a 35 kilometre rail spur, and the design allows for an additional 14 Mt/a expansion.
Work is progressing on a number of options for new mine development as part of the feasibility study to reach 320 Mt/a capacity. A decision is expected in early 2009.
Work also continued on pre-development studies for new mines.
2007 operating performance
Hamersley Iron’s total production in 2007 was 112.1 million tonnes, 14.9 million tonnes more than the 97.2 million tonnes in 2006. This result was notable for being achieved amid significant expansion work across several sites.
Shutdowns and flooding from two cyclones early in the year hindered operations significantly, although tie down procedures performed well. Several derailments also impacted operations significantly, resulting in an estimated 1.39 million lost saleable ore tonnage. Remedial action was undertaken on high risk sections and a rerailing project was approved which will eventually see 45 per cent of the network replaced.
Reinvestment in additional yard capacity, locomotives and rolling stock has been implemented to improve efficiency and remove bottleneck issues associated with limited rail capacity.
The Pilbara Blend product was successfully introduced mid year, winning widespread customer acceptance and at 100 per cent of the reference price. Pilbara Blend will comprise 15 per cent of the world’s seaborne iron ore trade.
Shipments by Hamersley Iron totalled 109.5 million tonnes, including sales through joint ventures. Shipments to China also reached a new record level at 59.6 million tonnes, confirming China’s place as the single largest, and fastest growing, destination for Hamersley’s iron ore.
| Million tonnes | |
|---|---|
| China | 59.6 |
| Japan | 30.0 |
| Other Asia | 18.3 |
| Europe | 0.7 |
| Total | 108.5 |
NOTE: This table includes 100 per cent of all shipments through joint ventures.