Hamersley Iron

(Rio Tinto: 100 per cent)

Upgrade to 220 Mt/a
RTIO is on schedule to have 220 Mt/a installed capacity in the Pilbara by the end of 2008, achieving a doubling of capacity since the beginning of the decade. The second stage of the Pilbara Expansion is well advanced with a further upgrade of Dampier Port, Yandicoogina mine expansion and Hope Downs stage 1 development now completed. The initial upgrade of Cape Lambert Port will complete the major infrastructure upgrades for this phase. Additional mine capacity at Hope Downs stage 2 to 30 Mt/a will match the capacities of mine, rail and port facilities at 220 Mt/a.

Pilbara 320/420 Mt/a
A suite of mine and infrastructure projects for the expansion of Pilbara capacity to 320 Mt/a is under study. The studies include a variety of greenfield and brownfield mine options across the Pilbara, expansions to both rail and port and supporting infrastructure, designed to bring the Pilbara capacity firstly to 320 Mt/a and then 420 Mt/a. The studies also contemplate the use of new technologies including a Perth based Remote Operations Centre, and a range of automation options. Underlying this work is an aggressive resource evaluation and definition programme, designed to ensure that resources are developed with optimal sequencing and timing. More than 400,000 metres of exploration drilling was completed during 2007 and a further 500,000 metres is planned for 2008.

Robe River Iron Associates

(Rio Tinto: 53 per cent)

Mesa A
The US$901 million Mesa A/Waramboo mine development is required to sustain production of Robe Valley pisolite, which would otherwise decline with the run down of the Mesa J resource. Pending finalisation of plans for the proposed rail spur to the existing line, transition work will begin shortly. Production at Mesa A is expected to commence in the first quarter of 2010, starting at 20 Mt/a, increasing to a 25 Mt/a rate from 2011.

Cape Lambert port
The first upgrade of Cape Lambert (from 55 Mt/a to 80 Mt/a) is well under way. A construction camp for 600 people has been established, and works are continuing according to plan with marine piling and bulk earthworks well advanced. The project scope includes extension of the wharf and upgrading of shiploading facilities to accommodate four capsize vessels simultaneously as well as upgrades to the stockyard with the addition of a new reclaimer. The project is scheduled for completion at the end of 2008 with progressive ramp up during the first half of 2009.

The 320/420 project
Cape Lambert is also the preferred site for expansion of Pilbara port facilities to 320 Mt/a, and conceptually to 420 Mt/a. Under the early planning for the 320 Mt/a, this would involve construction of a new terminal (Cape Lambert West) capable of berthing four capsize ships. That terminal would be extended to accommodate a further four berths according to the 420 Mt/a concept. Early planning has also identified the area to the west of the existing rail line for both stockpiles under both 320 and 420 Mt/a upgrade scenarios. This expansion plan carries the added benefit of not adding to Rio Tinto's footprint in the area.

Simandou

(Rio Tinto: 95 per cent)

The Simandou project in eastern Guinea, west Africa, is of great strategic significance for Rio Tinto. It is a greenfield discovery situated in one of the best undeveloped major iron ore provinces in the world. A prefeasibility study is studying the mining and transport options needed to bring Simandou into production as quickly as possible, with an initial capacity of 70 million tonnes per annum. The deposit has a targeted mineralisation of eight to 11 billion tonnes, and there is great potential in exploration opportunities across the project area. Total drilling of 50,000 metres was undertaken at the Pic de Fon and Oueleba sites in 2007, with an equivalent amount expected in 2008. Simandou has significant brownfield growth capacity, and conceptual development plans are already under way on expanding capacity towards 170 million tonnes per annum. These studies are scheduled for completion in 2010.

The International Finance Corporation (the private sector arm of the World Bank Group) retains a five per cent stake in the project and is working with Rio Tinto to develop it in an environmentally and socially sustainable way.

The project currently employs 375 Rio Tinto staff operating from offices in Conakry and Kerouane, and construction camps at Canga East and Oueleba in the Mining Concession. The total workforce, including contractors, is greater than 700.

Orissa, India

(Rio Tinto: 51 per cent)

Orissa is one of the key iron ore regions of the world. RTIO has a joint venture interest in Rio Tinto Orissa Mining with the state owned Orissa Mining Corporation. The joint venture holds rights to iron ore leases in Orissa, which it is seeking to develop. Although progress has been slow, Rio Tinto remains keen to participate in the development of the Indian iron ore sector through its joint venture. A project team has been established and is working to expedite the development of operations in India.

Rio Tinto has identified India as among the most likely economies to follow east Asia's development of a greater intensity of steel use. India's economy is expected to maintain its present growth rate, thus providing support for an expanding domestic steel industry. Rio Tinto has continued discussions with major domestic steel companies.